MDI Block 1 Commissioning Phase Test Sheet

Title: MDI Early Switch-on

Objective: Start MDI CCD Bake-out for Cleanliness

Outcome: MDI in Sleep Mode, CCD, Optics Package and filter oven temperatures within limits.

Procedures:

  1. 1.1 Switch on DEP & start CCD bake-out
  2. 1.2 Switch-on Filter Oven Heater
  3. 1.3 OP Thermal Adjustments
  4. 1.4 CCD Thermal Adjustment
  5. 1.5 End CCD Bake-out