MDI Commissioning Phase Block 1
MDI Block 1 Commissioning Phase Test Sheet
Title: MDI Early Switch-on
Objective: Start MDI CCD Bake-out for Cleanliness
Outcome: MDI in Sleep Mode, CCD, Optics Package and filter oven temperatures
within limits.
Procedures:
- 1.1 Switch on DEP & start CCD bake-out
- 1.2 Switch-on Filter Oven Heater
- m_ovenon - switch on prime oven controller
- m_ovenspt - set prime oven controller set point
- 1.3 OP Thermal Adjustments
- m_hopspt - set optics package heater set point
- 1.4 CCD Thermal Adjustment
- 1.5 End CCD Bake-out
This page last reviewed and revised 9 November 1995 - SDW